Our Journey Ahead – Project Timeline

Spring 2023

Plans for Our Cultural Heart masterplan approved.

Winter 2023

Surveys and preparation work taking place on site.

Summer 2024

Construction work on Phase One began:
library hub, food hall and public square.

January 2025

Funding approved for Phase Two:
museum and art gallery.

Summer 2026

Phase One – library hub and public square opened to public.

Construction work on Phase Two begins.

Summer 2027

Phase One – food hall opens to public.

Winter 2028/29

Museum and art gallery construction work completes. Internal fit-out begins.

Winter 2029/30

Museum and art gallery opens to the public.

From 2029

Delivery of future phases, including new urban park.